According to Reuters, a federal appeals court voided the record of decision for Sentinel Midstream’s Texas GulfLink project because its application area overlapped with another deepwater proposal, violating the Deepwater Port Act. The ruling, which took effect on October 30, creates regulatory uncertainty for the infrastructure development.

Environmental petitioners stated that the decision requires the Maritime Administration (MARAD) to revoke or suspend the license, halting construction on offshore components. While legal counsel for the petitioners argued that work cannot proceed without a valid federal license, Sentinel Midstream maintained that it is business as usual and that onshore work at the Jones Creek terminal continues.

Sentinel plans to petition the Supreme Court regarding the ruling. The company stated that the project, intended to load supertankers off the coast of Freeport, Texas, remains on track for a late 2028 operational date. However, court filings from the company previously noted that the regulatory cloud could harm its market position and impede offshore construction.

The appeals court decision may also affect other pending deepwater port applications with overlapping areas. MARAD expressed disappointment with the outcome, while continuing to support broader energy export initiatives.